Summary of Released MnDOT I-35W Bridge Documents: An Ugly Read
by Staff
Published: August 9,2007
Time posted: 1:00 am
Tags: Bridge Collapse, Document, Download, I-35W Bridge, Minneapolis, MnDOT, PDF, Transportation, University of Minnesota, URS
MnDOT has released five documents on its website relating specifically to the I-35W bridge (bridge number 9340) which we have
packaged
into a zip file (35 MB). The
files
include an outside consultant review, a
University of Minnesota Civil
Engineering field report, two brief status
summary documents, and, most
troubling, a MnDOT “Fracture Critical”
engineering summary which reveals in
candid descriptions and shocking photographs
the deterioration of many critical
bridge elements. Here’s my
summary of the relevant
parts of the documents, which we posted in our special Bridge edition of the Weekly Report last Friday:
A 299-page draft report prepared for MnDOT by
the URS Corporation of Minneapolis
entitled, “Fatigue Evaluation and Redundancy
Analysis” for Bridge No. 9340,
released July 2006.
-
It recommended “steel plating of all 52
fracture critical truss members” via
“additional plates bolted to the existing
webs” as the best retrofit option. -
The bridge was designed in accordance
with the 1961 AASHO
Standard
Specifications for Highway
Bridges - a completely different
fatigue design method that was
revamped in the 1974 interim edition.
“The poor fatigue details on the truss
spans, particularly those inside the main
truss tension chords that are
difficult to inspect, have raised
concerns on the the consequence of a
possible main truss member failure
triggered by a fatigue crack.” The 1961
AASHO specs don’t account for “bending
moments” on truss members; only
“axial force” is accounted for. -
URS developed a 3D model to simulate
stress on the bridge. Pages after 169
contain bridge failure simulations. -
Page 171-174 have eerie wireframe
simulations of bridge collapse:
computer-generated ghosts of future
events. Page 174 shows middle span
failure resembling the collapse video
released yesterday. -
Page 176 indicated a single upper chord
main truss member collapse would
cause more than a dozen floor trusses to
fail under eight different
simulated load conditions -
Page 231 has a drawing of major internal
collapse of center simulated from a
single truss chord failure -
Page 236 explores retrofit schemes: “Due
to the nearly double symmetry of
the structure, these eight members
actually represent thirty-two truss
members on the bridge.” Carbon-fiber
reinforced polymer plating (CFRP),
which “would be expected to take over the
member forces” but would be
difficult to apply and “determined
inappropriate” as a potential patch.
Pre-tensioned bars are deemed
inappropriate due to non-satisfactory
performance -
Page 265 considers high-performance steel
plating as the most suitable.
Design loads were determined from the 3D
computer model, and new plates
would have to be installed extremely
carefully to avoid increasing stresses. -
Page 267 says replacing the deck would
provide better strength by more
widely distributing the load. -
Page 299: in the conclusion someone
underlined the passage: “it is more
desirable to keep this symmetrical
loading condition during deck replacement
as much as possible,” meaning that load
symmetry across both sides should be
maintained while work is underway, since
removing either the northbound or
southbound decks alone would introduce
even more stress to the structure.
The brief MnDOT Structure Inventory Report (3
pages) for the last inspection on
May 15, 2006, (which was generated and posted
by MnDOT on August 2, 2007)
indicates the deck was 6% unsound. Condition
codes were: Deck: 5;
Superstructure: 4; Substructure: 6; Channel:
7. Appraisal ratings were:
structure evaluation: 4; Deck Geometry: 4;
Underclearances: 7; Waterway
Adequacy: 9; Approach Alignment: 8. The
in-depth inspection for “fracture
critical” status was on a 48-month cycle
apparently last performed May 2003.
Underwater inspections were on a 60-month
cycle last performed December 2004.
Bonus: 15% of the paint was unsound, it was
painted in 1968, the primer type was
“LEAD,” and the finish was “OTHER (UNKNOWN),”
though the more detailed Fracture
Critical report has more information about
repainting.
The Bridge Inspection Report (4 pages) has
all the noted inspection issues going
back to the 1970s. Current highlights include
Element 412: “Relief joints need
re-sealing”; Element 131: “Main truss members
have numerous poor weld details
(some cracked tack welds)”; Element 984:
Drainage: “Pier 6: horizontal drain
trough has inadequate slope (usually
clogged).”
The March 2001 University of Minnesota
Fatigue Evaluation of the Deck Truss of
Bridge 9340 by Heather M.
O’Connell,
Robert J.
Dexter, P.E., and
Paul M.
Bergson, P.E., conducted by the
Department of Civil Engineering, used strain
gages to measure the effects of
load stress upon the bridge members.
-
Researchers installed “on main trusses
and floor truss to measure the live
load stress ranges.” While trucks of
known weight crossed the bridge,
researchers measured the stress gages
then developed computer models to
calculate stress ranges throughout the
deck truss. -
The Abstract notes “the bridge’s deck has
not experienced fatigue cracking
but it has many poor fatigue details on
the main truss and floor truss
system,” and they concluded that “fatigue
cracking of the deck truss is not
likely.” The project also “verified that
the use of strain gages at key
locations combined with detailed analysis
help predict the bridge’s
behavior.” -
Pages 54-57 have interesting charts of
stress measurements -
After page 68, simulation data renders
results impressively similar to their
field stress tests. That’s some quality
computer modeling.
Finally, the most grim
50-page report
came from MnDOT engineers in June 2006.
Entitled “Fracture Critical Bridge
Inspection: In Depth Report” for “Bridge
#9340 (Squirt Bridge)”. MnDOT engineers
reported a profusion of “pack rust,” which is
essentially the
formation
of rusting cavities between steel
members. The executive summary is grim:
If bridge replacement is
significantly delayed, the bridge should be
re-decked. The design of the main river spans
do not allow for deck widening.
Any re-decking contract should also include a
complete re-painting of the
superstructure, elimination of the hinge
joint in span #2, and reconfiguration
of the deck drainage system.
![[Print]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/print.png)
![[Email]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/email_2.png)
![[RSS Feed]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/rssfeed.png)
![[Digg]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/digg.png)
![[Facebook]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/facebook.png)
![[MySpace]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/myspace.png)
![[StumbleUpon]](http://politicsinminnesota.com/wp-content/plugins/dmc_sociable_toolbar/stumbleupon.png)

POST A COMMENT